I've just completed my first job on Leisure Isle, Knysna, South Africa. The patio, pool deck and entrance measured up to 152 sq m (1663 sq ft). It took me a month to complete as rain held me up. The surface of the tiles were very badly erroded and I had to grind away the effected areas, apply epoxy, then covered with silica sand and finally i started applying the skim coat. The client wanted me to do a full splatter in TF Sandstone, slightly knocked down, with a 50 % coverage of TF Limestone on top. A lot of my time was taken up by difficult screening of the pool edges as well as the walls. During this time I made quite a few emergency calls to my distributors in PE, Ian and Graig, and also to a fellow installer Henk - thank you guys, you helped me out a lot.